Executive Overview
Project Bruno · Infoblox IPO Readiness · For Executive Staff review
- Data Privileges (Darshan) — on track to latest deliverable; MNPI workplan formalization underway Reported 2/10
- 13 of 14 workstreams have not yet posted a WS Status update; status below is rolled up from each workstream tab
- Active In-Progress: F&R quarterization (Riveron + Deloitte), SOX risk assessment & ITGC walkthroughs, Treasury ICD portal & Wells Fargo RFP, Anaplan implementation, Optimus Aug-26 go-live tracking
- 14 workstreams mobilized · advisors engaged · governance and SOX frameworks scoped
- Get WS Status entries from 13 outstanding owners ahead of 5/14 ESTAFF
- Confirm Mock Earnings schedule — key 5/14 ESTAFF agenda item
- Surface IPO counsel selection with Vista/Warburg; engage earlier than standard 6-month window
- Resolve Internal Comms ownership (Katie Howard candidate)
- Hire Equity Stock Administrator (then they lead system selection) and Head of IR (6–9 month lead time)
- Decide SOX co-source / outsource model before Optimus go-live
- WS Status visibility gap — 13/14 owners owe an update Open
- 9 tasks overdue ≥11 days: ServiceNow GRC (Legal), BC/DR Council (Cyber), SB 261 + AB 1305 (Inclusion), ERM Leadership (SOX), Deloitte tax quarterization coord, Controlled Co. doc, Corporate Narrative, Equity Story workplan
- Optimus / Oracle go-live (8/26) — single biggest SOX risk; all ITGCs need re-walking Watch
- IPO counsel selection unresolved with Vista/Warburg sponsors
- MNPI blackout philosophy (all-employees vs. restricted) pending board decision
- Cyber team ~1 year short-staffed; CISO hire flagged At Risk
Next 30 / 60 / 90 Day Priorities
Through August 2026- Forecast & Guidance test run (5/5)
- Mobilize SOX scoping & design gap (5/5)
- Determine board structure (6/1)
- Catch up 13 outstanding WS Status updates
- Resolve Internal Comms ownership
- Engage external IPO counsel
- SOX risk assessment complete
- FY25 historicals quarterization complete
- FedRAMP audit close-out
- ICD portal full migration
- Best Practice Work Q4 milestone (7/31)
- Kick off Equity Work (8/5)
- Optimus / Oracle Fusion go-live (8/31)
- Equity stock administrator hired
- Lead underwriter shortlist
Key RAID Items
Risks & decisions for executive visibility · 0 high · 0 medium · 3 lowAsks of Executive Staff
Where we need your supportAINarrative
Auto-generated from WS Status tab + 14 workstream schedules · refreshed May 14, 2026Project Bruno is on track to meet its May 28, 2027 IPO effectiveness target. Over the past quarter, the program completed mobilization across all 14 workstreams, secured the advisor stack (PwC, Deloitte, Riveron, Compensia, Mercer/Radford), and baselined audit-readiness gaps in finance, SOX, tax, and HR. We have approximately twelve months of foundational and uplift work ahead of the SEC filing window, with sufficient runway provided we hold to the Org Meeting (Dec 2026) and Q1'27 mock close as anchor dates.
The most material executive-level decisions in the next 90 days are: (1) selection of IPO counsel and lead underwriters in coordination with Vista & Warburg, (2) approval of the SOX co-source/outsource model, and (3) the MNPI blackout philosophy decision (all-hands vs. restricted population).
PM Overview
Program management view · 14 workstreams · IPO effectiveness 5/28/2027 · $11.17M budget
Workstream health
14 workstreamsNext key milestones
From 5/11/26Attention needed this week
Overdue or at risk| Item | Workstream | Owner | Due |
|---|
Recent status updates
Last 7 daysWorkstreams
14 workstreams with individual plans. Click any card for the owner's detail sheet.
Milestone Timeline
Tasks flagged Key Milestone = Y on each workstream tab, plotted against the 22 program milestones from the Inputs sheet (cells B16:B42).
Filing cadence
Mock closes
Board milestones
Milestone Alignment
Tasks tagged to a named IPO milestone (Org Meeting, DRS, Public Filing, etc.) vs. tasks pegged only to a calendar month. Month-pegged tasks won't auto-shift if the IPO date moves.
Alignment by workstream
Ranked by count of unaligned tasksPriority realignment targets
Recommended triageFinancial & Regulatory Reporting (84 unaligned, 87%) and SOX (54, 86%) carry the largest absolute backlog of month-pegged tasks — driven by technical accounting memos (ASC 842, 805, 280, 350, 260, 718) and SOX control documentation / ITGC walkthroughs.
Planning & Forecasting (94% unaligned) and Tax (90%) are the worst on a percentage basis. Both are core to the Q1/Q2 mock closes and guidance readiness — a slip here cascades directly to filing dates.
Legal (37%) and Equity Story / IR (35%) are the healthiest — most work is tied to Org Meeting / DRS / Filing / Launch / Effectiveness, which is how IPO counsel naturally structures plans.
Treasury (85% unaligned) looks misleadingly bad — most Treasury work is best-practice / ongoing operational uplift that legitimately does not flex with the IPO date. Lower priority to realign.
How to realign a task
For workstream owners- On your workstream tab, locate the Program Milestone column.
- If the cell shows a month (e.g.,
Oct-26) or-, pick a named milestone from the Inputs sheet: Org Meeting, Initial DRS, DRS/A, Q1'27 Mock Close, Q2'27 Mock Close, Public Filing, Launch, Effectiveness, First 10-Q/10-K. - If truly no milestone applies (pure operational BAU), keep the month — but mark the task as "Best Practice / Ongoing" in the Category column so it's excluded from slip analysis.
- Focus realignment effort on tasks due before Q1'27 Mock Close — those are the ones most likely to cascade if the IPO date shifts.
Workstream detail
14 of 14 workstreams · 5 estimated (owners to validate)| Workstream | Leaf tasks | Aligned | Not aligned | % not aligned | Primary drivers of misalignment |
|---|
RAID Log
Open risks, actions, issues, and decisions · 0 High · 0 Medium · 3 Low
Open items
From RAID log sheetProgram Team
Program managers, workstream leads, and participants from the Team Members sheet.